REPORT ON THE COMPLETION OF PHASE ONE PROJECT BY TRUWAYLIF FOR TAMPION AND ZIENG

The main activities that were left for the phase one project was the electricity extension and connection to the project sights and the general training of soya beans processing which have now being completed .The electricity was extended to the centers after the release of the funds for both Tampion and Zieng. The Projects (grinding mills) are now completed and fully functional.

TRUWAYLIF have performed the following activities that make the projects fully functional: We have met with the contractor and discussed the terms and conditions of contract and we all agreed before the work was done. The project coordinator with the contractor went to market and did a survey before the purchased was done.

TRUWAYLIF organized the materials and rented a car and transported them to both Tampion and Zieng respectively on 10th January, 2020. After the materials were sent to the communities, the Savelugu Municipal VRA supervisor went to the centers and supervised the materials on 22nd January, 2020 before the contractor started the work. You may refer to the following pictures for evidence.

The work was done by the contractor after the Savelugu municipal VRA officer went and survey the projects site. The planting of the poles was done on the 25th January, 2020 at Tampion and the next day wiring and extension followed.

The milling machines were connected and powered on the 27th January, 2020 for both Tampion and Zieng respectively. The following pictures throw more lights on what was done.

TRUWAYLIF also met with the groups committee members for both Tampion and Zieng to discuss the way forward of the project. We discussed the following: how the machine will be operating, the maintenance of the center, how the funds of the center will be managed, how to expand the business in the near future, whom our targeted customers are, how to benefit from our businesses and so on. The committee pictures are as follows.

The second committee and stakeholder meeting were done to plan and fix the date for training, the commissioning and the handing over to the beneficiary communities.

Figure 1 Stakeholders consultation meeting to plan for the training and commissioning

These are the pictures during the committee meetings at Tampion and Zieng

The following pictures was taken during the soya beans food processing training

Frying soya beans, maize and groundnut to make soya beans porridge

Milling the soya beans, groundnut and maize

Soya porridge

 Preparing soya koshi

 Frying soya koshi

Soya milk preparation

Boiling the soya milk

Preparing soya kebab

Cutting to fry the soya kebab

Frying the soya kebab

Prepared soya kebab

 Prepared soya beans food ( soya milk, kebab, koshi, porridge and tobani)

DURING COMMISSIONING OF THE AGRO-PROCESSING CENTERS FOR TAMPION AND ZIENG PROJECTS

OPENING PRAYER

MADAM ROSINA ZENABU ABDUL-RAHAMAN (CEO OF TRUWAYLIF) DELIVERING HER SPEECH

TAMPION CHIEF REPRESENTATIVE GIVING THANKS TO TRUWAYLIF AND UNDP/AFP

THE GUST SPEEKER (NORTHERN REGIONAL AGRIC. DIRECTOR) GIVEN A SPEECH

TAMPION YOUTH LEADER (ZAACHI)

TAMPION ASSEMBLY MAN (HON. ALHASSAN)

 

UNDP/AFP  REPRESENTATIVE (Mr. ABU, EPA DIRECTOR) MAKING A PRESENTATION

DISTRICT CHIEF EXECUTIVE FOR NANTON AND THE CHAIRPERSON FOR THE COMMISSIONING CEREMONY MAKING REMARKS

INTRODUCTION OF GUST AT ZIENG BY THE M.C

SOYA BEANS FOOD PREPARED AND READY TO BE TASTED BY DIGINITORIES DURING THE CEREMONY

With regards to the phase one, TRUWAYLIF have finished with everything and the machines and everything is completed and fully functional now. We are therefore requesting that UNDP/AFP release the forty percent (40%) of the funds left for TRUWAYLIF at once.

Thank you.

                                                       Rosina Zenabu Abdul-Rahaman

                                                          (Executive Director – TRUWAYLIF)

                                                                      0207413877/0246731874